Providing daily engineering and assistance to the development of a 1.3-million-ton-per-year underground limestone mine in northeastern Missouri.

Project Details

Continental Cement

2011 - 2013

Missouri


Continental Cement hired RESPEC to help in developing its underground limestone mine, which was a multiyear project that included a comprehensive mine design. The original mine design options developed during the feasibility study were assessed based on several important variables. RESPEC conducted in-depth geologic mapping of the project site and nearby properties to provide a detailed understanding of the localized geologic stresses. Furthermore, the ultimate mine design was actively evaluated during the development phase, which included chemical testing of the limestone to confirm the validity of the original chemistry model. RESPEC continuously worked with the client to develop accurate and in-depth short- and long-term mine plans for the operation.

RESPEC designed and wrote the bid packages for many aspects of the project; the bid process minimized the overall cost of the project to the client. Individual bid items included major tasks such as overall mine development, surface excavation work, decline construction, reclaim tunnel construction, and shaft construction. Bid items also focused on infrastructure such as the conveyor and conveyor belt manufacture and installation, the underground crushing system, the electrical and communication systems, and the water-control system. Additionally, RESPEC managed the bidding of mining equipment, grout installation, and other miscellaneous infrastructure needs.

The development oversight included weekly operations of the project; advancement meetings; roof-monitoring and stability-control surveys and ventilation surveys; blast optimization, monitoring, and damage-mitigation guidance; infrastructure surveys and cave mapping; and mine-safety and regulatory-compliance advice.

Continental Cement also asked RESPEC to assess the damage potential that airblast from underground blasting would have on permanent underground structures while developing their underground limestone mine. RESPEC conducted an industry and literature review on the current knowledge of underground blast pressures. While the survey showed a significant lack of research in this study area, RESPEC used the limited data to estimate the expected blast pressures on the mine's permanent fan wall, which was undergoing installation. RESPEC used that estimate to specify and acquire advanced monitoring equipment that could be used to gather empirical data from the mine. RESPEC determined the optimum setup for the equipment and acquired data to complete the study. After reviewing the data, RESPEC determined that the design strength of the fan wall was sufficient to withstand the blast pressures.

RESPEC also analyzed the nature of the blast pressures because this topic has not been thoroughly studied.