Leachate Treatment Plant Upgrade Design/Permitting
Leachate Management System evaluation, design, multiple upgrades and permitting of a 25-year-old, 100,000 gallon/day treatment facility
Project Highlights
- Replaced system with a 150,000 gallon/day MBBR plant with physical and chemical treatment
 - Biological denitrification / nitrification technology
 - DAF clarification prior to discharge to POTW
 - Added 360,000 gallons/day RO system to allow for the potential to stream discharge treated leachate
 - Cost-Benefit Analysis
 - Strategic Expansion Phasing
 - Advanced Effluent Compliance
 - Capital & Operating Cost Assessment
 - System Design
 - NPDES and WQM permitting with PA DEP
 
Benefits (Engineering, Economics, & Environment)
- Enhanced Leachate Treatment Capacity
 - Uninterrupted plant operation during construction/demolition
 - Plant Efficiency Optimization
 - Provided a sustainable and cost-efficient operation to avoided POTW-issued discharge surcharges
 - Informed Financial Decision Making with development of a comprehensive cost-benefit analysis
 - POTW and Stream Discharge Capability and Compliance
 
		  
	